Projects
Complex Land Use Development
General Plan Amendment, Zone Change, Conditional Use Permit, Public Hearing




Fjora's founder had the privilege of serving as the lead developer for a prominent California builder, where she identified a 7-acre vacant parcel in Carlsbad. She successfully processed a general plan amendment, zone change, and conditional use permit, paving the way for the construction of a 270,000 sqft luxury senior community. This experience highlights her expertise in navigating complex development processes and her commitment to creating exceptional living spaces.
Solving Regulatory Hurdle
Permitting, Client Advocacy, Collaboration



Fjora Projects successfully navigated the intricate permitting process for a homeowner who needed to build a retaining wall to stabilize their leaning house. Complicating matters, old mapping indicated that the proposed wall was located in a public right-of-way dating back to the late 1800s. After a year of addressing regulatory hurdles and collaborating with local authorities, the necessary permit was secured, allowing the homeowner to proceed with construction and safeguarding their property.
Multi-Phase Residential Landscape Installation
Entitlements, Permitting and Client relations

This is a place holder

This is a place holder
Fjora Projects collaborated closely with a contractor, client, and landscape architect to navigate the new Site Plan and Architectural Review process in Petaluma, CA. Despite initial frustrations from all parties, Fjora facilitated clear communication and coordination, instilling confidence and calm in the client throughout the process. By effectively addressing concerns and working collaboratively, we secured the necessary entitlements and processed the building permits, making the overall approval process much simpler and seamless. This experience exemplifies Fjora's commitment to ensuring a smooth development journey for our clients.
San Jose Stopped Construction
Construction Compliance Consulting


During the construction of a multi-million dollar care facility, a new local official halted progress due to compliance concerns over a historic part of the property. The construction team lacked the expertise to address these issues, risking thousands in daily losses.
In response, Fjora Projects' founder compiled a detailed 600-page document over three days, containing all necessary reports and approvals. This thorough presentation enabled the official to quickly understand compliance, allowing construction to resume within days. She handled the issue with grace and efficiancy.
Community Engagement for Controversial Project
Land Development, Use Permit, Public Hearing




​While working for a prominent builder, the founder of Fjora Projects led public relations for a controversial Southern California project. Despite mixed community support, she organized numerous public presentations and meetings, exceeding inclusion requirements. By engaging with neighbors and addressing concerns, she coordinated with experts and local officials on noise, traffic, and emergency response, ultimately securing City Council approval. The now-constructed project is regarded as a positive addition to the community.
Historic Property Relocation and Preservation
Entitlements, Renovation, Project Management




The founder of Fjora Projects oversaw and spearheaded the moving and restoration of a historic landmark in San Jose to facilitate the construction of a larger building by a developer, who funded the restoration. The home, which was in disrepair, underwent an extensive process that required securing a historic preservation permit and approval from the City of San Jose Historic Commission to relocate it 60 feet from its original site. Under her leadership, the restoration ensured that not only the home but also the outbuildings and landscaping were historically accurate. Today, the landmark is open to the public, showcasing the successful balance between development and preservation.